Data Centre Watch Updated 25 October 2026, 14:12 UTC

Data Centre Watch

Illustration: a matte, monolith-like data slab standing alone in a wildflower meadow, black cables fanning from its base into the soil like roots, a lone oak and a low sun behind.

The local fight over one field is one row in a national rush. This is a rolling, fully sourced record of what changed — the schemes, the planning decisions, the power and water, and the wider world picture.

108

days under a hosepipe ban

Under a hosepipe ban for 108 days — since 10 July 2026 (as of 25 October 2026).

Affinity Water — Central region (incl. WD5), extended to the East region

11 areas in drought, parts of 4 in severe · reservoirs 54% · the water picture →

Source: Affinity Water — Temporary Use Ban

Latest

63 entries matching · showing 46–60

  1. World Finland / South Korea / India Reported

    Three more gigawatt-scale plans — Finland, Korea, India — on paper only

    Sesterce plans a '€10bn' AI campus at a former Finnish paper mill (200MW first, then 600MW, aiming past 1GW); Sejong signed an MOU for a 360MW AI data centre (₩7tn through 2029); ReNew signed an MOU for a 750MW 'green' park near Mumbai. None shows financing, land, a grid deal or permits — all are announcements or MOUs.

    Why it matters: A headline number is not a built data centre: the gap between the press release and the energised site is the whole story.

    Source: TSN Media [C]

  2. World Global Reported

    Data-centre fires and power failures have doubled since 2024

    The Energy Incident Register counts 8 electrical fires/power failures at data centres in 2024, 20 in 2025 and 19 already in 2026 — nearly half of its 93 incidents since 2010 clustering in the last three years. UPS and battery rooms (22) and backup generators (15) are the most common named failure points.

    Why it matters: The build-out's physical fragility: more power density and compressed commissioning schedules, failing most often in the power gear.

    Source: Energy Incident Register / DCD [C]

  3. World United States Reported

    Broadcom, Apollo and Blackstone launch a $35bn AI-infrastructure venture

    Broadcom and the asset managers Apollo and Blackstone have formed a $35bn partnership to expand advanced AI computing capacity — another sign of the capital now chasing data-centre build-out.

    Why it matters: The money is getting bigger and more financialised — the financing side of the boom, again.

    Source: CNNBC [C]

  4. World United States Reported

    US: about half of 2026's planned data-centre capacity delayed or cancelled

    Analysts put roughly half of the ~12GW of US data-centre capacity planned for 2026 as delayed or cancelled, with PJM wholesale prices up ~76% year on year and ~2,061GW stuck in interconnection queues. Local opposition has hardened: 379+ US jurisdictions now have moratoriums or bans, with ~$68bn of development stalled.

    Why it matters: The binding constraint is now power and permits — and the backlash has become a nationwide planning fact.

    Source: Achilles / inprofile [C]

  5. World United States Reported

    Nvidia forms an alliance to build a 'power-flexible' AI data centre

    Nvidia has assembled partners into an alliance to build an AI data centre designed to flex its power consumption rather than demand a fixed maximum feed — a move upstream into the electricity bottleneck that gates its own accelerator market. Partners, capacity and timeline were not disclosed.

    Why it matters: The chipmaker is now organising around power, not just silicon — because that's what caps how many chips can run.

    Source: Die Signal / Yahoo Finance [C]

  6. World Israel 64 MW Reported

    Nvidia plans Israel's largest server farm ($1.5bn, 64MW)

    Nvidia is set to lease a 30,000 m² facility near Yokneam for a 64MW Blackwell-powered site, part of a push making Israel its second-largest R&D hub outside the US.

    Why it matters: The chipmaker moving further into owning the buildings, not just the chips.

    Source: G&B Daily News [C]

  7. World United States 2000 MW Reported

    AMD and Anthropic plan up to 2GW of MI450 compute

    A strategic partnership to deploy up to 2GW of AMD Instinct MI450 GPUs in Helios rackscale systems, with the first gigawatt from H1 2027 — a challenge to Nvidia's lock on AI capacity.

    Why it matters: Compute supply is diversifying, but every gigawatt still lands on the same grid.

    Source: DailySynapse [C]

  8. UK National Reported

    Regen: a 1GW gas data centre could emit up to 5.7 Mt CO₂ a year

    Regen estimates a 1GW gas-fired data centre could emit 2.7–5.7 million tonnes of CO₂ a year, and that of 152 UK applications only 13% mention on-site generation and 9% state a connection type. It calls for mandatory power disclosure in applications and a moratorium on gas-primary schemes.

    Why it matters: The disclosure gap, in numbers — most applications don't say how they'll be powered, in a country promising net zero.

    Source: Armason weekly [C]

  9. UK National Reported

    The UK's data-centre pipeline: 173 projects, 14.6GW against ~1.6GW existing

    Analysis puts the UK pipeline at 173 committed projects totalling ~14.6GW of planned capacity, versus ~1.6GW of existing capacity — a tenfold gap. It also cites UK power costs at roughly four times US levels (an estimated £226m a year for a 100MW site) and ~1.9bn litres of English data-centre water use a year that operators aren't required to report.

    Why it matters: The scale of what's proposed, the price of power, and the water nobody has to disclose — in three numbers.

    Source: Servnet / Computer Weekly [C]

  10. World Texas, US 1000 MW Reported

    Nvidia reported to take a 1GW Texas data-centre lease

    Nvidia is reported as the tenant behind a lease worth up to $50.2bn at Hut 8's one-gigawatt Beacon Point campus — using its balance sheet to underwrite the project. Neither company has confirmed the tenant.

    Why it matters: A chipmaker now financing, not just supplying, the buildings — and it revives the 'circular AI financing' question.

    Source: Paris Times [C]

  11. World Mississippi, US Reported

    Entergy warns AWS of peak-time disconnections in Mississippi

    Entergy Mississippi told AWS its Jackson-area data centres could be disconnected at peak demand — reported as the first formal interruptible-service notice to a hyperscaler. AWS built 'Project Falcon', an automated switch from grid to backup generation, in response.

    Why it matters: The grid can't always carry the load — even for the largest operators, on the hottest days.

    Source: TokenPost [C]

  12. World India Reported

    India's grid strains as AI data-centre demand surges

    Regional power committees are weighing data-centre load, upgrade costs and the risk of 'abrupt load rejection' as operators bulk-buy electricity; transmission upgrades are running into cost and right-of-way delays.

    Why it matters: The same grid-and-water squeeze as the UK, arriving at gigawatt scale in a different system.

    Source: The Hindu [C]

  13. World Utah / Texas, US 2450 MW Reported

    Oracle trucks in gas to keep data centres on schedule

    With pipelines delayed, Oracle has compressed natural gas delivered by truck: it kept a Salt Lake City-area site running for over a year, is doing the same at its OpenAI campus in Shackelford County, Texas, and is weighing it for the 2.45GW Project Jupiter in New Mexico — where it has already sent a force-majeure notice.

    Why it matters: When the grid and the pipes can't reach the site, the fuel arrives by road — the lengths the build-out will go to.

    Source: Bloomberg via Quartz / DCD [C]

  14. UK London / national Reported

    A UK firm pitches 'election-grade' data to defeat planning opposition

    Amphio Technologies, a US-funded UK company incorporated in August 2026, is offering developers mass public-opinion measurement 'modelled down to individual neighbourhoods' — election-style intelligence aimed at defeating data-centre and infrastructure opposition. Founder James Yucel (previously real-estate private equity, the Onward think tank and Focaldata) points to opposition groups doubling to 833 across 49 US states in early 2026 and a May 2026 Gallup poll in which 71% opposed a data centre near their home.

    Why it matters: The counter-offensive: developers are buying the same machinery that wins elections — worth knowing that some planning arguments are being engineered, not just made.

    Source: Green Street News / Amphio [C]

  15. World United States Reported

    Local opposition has cancelled $260bn of US data centres this year

    Heatmap Pro counts at least $260bn of US data-centre investment cancelled in 2026 after sustained local opposition — about $130bn of it in the three months to 30 September alone, more than in the whole of last year. Roughly $1trn of projects now face organised opposition, and about half of the projects that met backlash this year were ultimately dropped.

    Why it matters: The backlash is not noise — it is now a measurable brake on the build-out, the clearest evidence that the local fight works.

    Source: Heatmap Pro [C]

Watchlist — what lands next

WhatStateWhen
Data-centre National Policy Statement (NPS) Still unpublished; projects already being directed into the NSIP regime without it. Expected 'shortly after' the Jan 2026 regulations
Ofgem 'Curate' data-centre connection reform Consultation closed 17 Sep 2026; decision pending — commitment fee £237,500–£712,500/MW. Decision later in 2026
Scotland — hyperscale planning guidance Parliament agreed no decisions on hyperscale applications until guidance is published. Guidance expected by December 2026
Draft London Plan — data-centre policy GLE3 Consultation closed 15 October 2026; responses under consideration. Next draft / adoption pending
National Scheme of Delegation for planning functions (SI 2026/854) Standardises which applications go to officers vs committee; non-compliant committee decisions open to judicial review. In force 31 October 2026
EU data-centre standards and rating scheme Commission has adopted a data-centre sustainability rating scheme; consultation on minimum performance standards remains open. Consultation closes 14 December 2026
Environmental Audit Committee report (HC 22) Inquiry 'Risks and opportunities to the sustainability of data centres in the UK'; report + government response due. Awaiting publication
Three Rivers Local Plan examination Plan submitted; examination in H1 2027, adoption targeted Sep 2027. Submission 30 November 2026

Join our WhatsApp group

Get the latest on the consultation, the examination and what happens next — straight from the campaign.

Subscribe by RSS/Atom

Follow the campaign in any feed reader (Feedly, NetNewsWire, Thunderbird, Inoreader…) — no account, no emails, no tracking.

Right-click → copy the link and paste it into your reader, or click if your browser opens feeds directly.

Fully sourced, no invented numbers

Every entry names its source and how it is known — verified, a designated claim, our calculation, or a gap. Where a claim is contested, we say so. See all reports & explainers →