Local Plan evidence Water

Last updated 23 October 2026, 10:20 UTC

The water deficit, in one place

The draft Local Plan would add 1,300 homes and a 96 MW data centre to a district that is officially an area of serious water stress — currently under a legally enforced hosepipe ban, in drought, over a globally rare chalk stream. This is the whole water picture, in one place.

106

days under a hosepipe ban

Under a hosepipe ban for 106 days — since 10 July 2026 (as of 23 October 2026).

Affinity Water — Central region (incl. WD5), extended to the East region

11 areas in drought, parts of 4 in severe · reservoirs 54% · the water picture →

Source: Affinity Water — Temporary Use Ban

Where the water comes from

Abbots Langley sits over a chalk aquifer, and its river — the River Gade — is a chalk stream. Chalk streams are among the rarest river habitats on Earth: around 85% of the world’s are in England, and Hertfordshire holds roughly 10% of England’s ~220.1 They are fed mostly by groundwater, which is why the chalk beneath our feet is the river.

The district is officially classed as an area of serious water stress.2 The River Gade is already rated “poor” and over-abstracted — and after restoration work, a 2021 fish survey found it “near desolate” before recovering to a handful of trout by 2025.3 It is a river that can come back — but only if it is given the water to do it.

Right now, today

This is not a future risk. As this is written:

Figures as of the Environment Agency’s weekly drought report for 16–22 October 2026 (published 23 October), the September 2026 monthly summary (13 October), the severe-drought declaration of 15 October, and the 20 October drought direction. England has had 52% of its October rainfall; the National Drought Group next meets on 28 October.

Groundwater levels continued declining at all indicator sites. A flash drought was declared. Hertfordshire had its driest July since records began in 1871.

Environment Agency · Hertfordshire & North London water situation, July 2026

The squeeze: less water, not more

The direction of travel in this catchment is the opposite of growth. The Environment Agency is unable to grant new abstraction licences from surface water and most groundwater here.7 In the Gade valley, Affinity Water is reducing abstraction by 6.4 million litres a day to protect the chalk stream.8

Meanwhile demand is up about 20%; the Central region received just 1% of its average July rainfall; and the company warns it may have to “stop or limit how much we take” from some sources before the year is out.9

The company’s own Water Resources Management Plan is built on cutting use and finding new supply — but admits that demand management “won’t be enough”, and the first major new supply schemes are not due until the 2030s and 2040s.10 Less water available, stricter standards: that is the plan the Local Plan must fit around.

Downstream: the sewers are already full

Wastewater matters as much as supply. The works that take Abbots Langley’s sewage — Maple Lodge — serves around 500,000 people and can receive up to 300,000 cubic metres a day, discharging to the Grand Union Canal and the River Colne.11

So the extra foul flow from 1,300 homes and a 96 MW data centre would arrive at works that are already spilling, while the plan’s own water assessment simply assumes the existing works can cope.15

The unknown at the centre

Here is the number nobody has published: the water demand of the 96 MW data centre already approved at Bedmond Road.16 Data centres are water-hungry, and this one is the single largest new user beside the site — yet its potable demand is not in the public record.

The plan itself tells the housing developer to account for it, but no combined water budget for the catchment exists, and there is no cumulative assessment of the homes, the data centre and the other schemes together. The council’s own evidence calls these catchments “highly sensitive to the cumulative impact of development” — and then assesses the sites one by one.17

That gap is national, not local. The Environment Agency told the Environmental Audit Committee that the evidence base “remains incomplete, because data centres are not required to report site-level water use” to the regulator — the sector is under 1% of public supply nationally, but “an individual development may be significant locally” — and suggested the largest non-household customers publish their usage and say what they are doing to become more efficient.24

Sources

  1. Wild Trout Trust & WWF, The State of England’s Chalk Streams — wwf.org.uk.
  2. Environment Agency, Water stressed areas — final classification (2021) — gov.uk.
  3. Colne Catchment Action Network, Channel restoration, Gadebridge Park (fish survey 2025) — colnecan.org.uk.
  4. Affinity Water, Temporary Use Ban — Central region (statutory notice, 2026) — affinitywater.co.uk.
  5. Environment Agency, Dry weather and drought in England: 9 to 15 October 2026 — gov.uk.
  6. Environment Agency, Hertfordshire and North London water situation: July 2026 — gov.uk.
  7. Environment Agency, Colne catchment abstraction licensing strategy (2026) — gov.uk.
  8. Colne Catchment Action Network, Restoring sustainable river flows — River Gade — colnecan.org.uk.
  9. Affinity Water, Our water resources position — affinitywater.co.uk.
  10. Affinity Water, Final Water Resources Management Plan 2024 (WRMP24) — affinitywater.uk.
  11. MHCLG / Planning Inspectorate, Maple Lodge STW — IED containment options report (Oct 2023) — gov.uk.
  12. Three Rivers District Council, Infrastructure Delivery Plan (July 2026) — threerivers.gov.uk.
  13. Environment Agency, Event Duration Monitoring — storm overflows annual returns; Watford Observer, Storm Henk (Jan 2024) — data.gov.uk.
  14. Find a Tender, K298 Maple Lodge STW AMP7/AMP8 new permit — contract award (2026); Thames Water, AMP8 Delivery Plan progress — find-tender.service.gov.uk.
  15. Three Rivers District Council, Habitats Regulations Assessment (July 2026) — threerivers.gov.uk.
  16. MHCLG / Planning Inspectorate, Recovered appeal: land off Bedmond Road (12 May 2025) — gov.uk.
  17. Three Rivers District Council, Local Plan Part I: Policies (July 2026) — threerivers.gov.uk.
  18. Environment Agency, Water situation: September 2026 summary (national monthly report, updated 13 October 2026) — gov.uk.
  19. DEFRA / Environment Agency, Government activates plan to protect consumers as severe drought declared in parts of England (15 October 2026) — gov.uk.
  20. DEFRA / Environment Agency / Emma Hardy MP, Water company bosses update National Drought Group on resilience (published 20 October 2026) — gov.uk.
  21. BBC News, Water leaks ‘unfixed for months’ in drought in southern England (21 October 2026) — bbc.co.uk.
  22. Exmouth Journal, Devon water restrictions spark Exmoor farmer’s warning (21 October 2026) — exmouthjournal.co.uk.
  23. Somerset County Gazette, Somerset MP calls for farm reservoirs amid severe drought (21 October 2026 — Wimbleball at 16%) — somersetcountygazette.co.uk.
  24. Environment Agency, Written submission to the Environmental Audit Committee: risks and opportunities to the sustainability of data centres in the UK (DCU0093) — committees.parliament.uk.
  25. Harrow Online, Major flooding closes Wealdstone High Street following burst water main (23 October 2026) — harrowonline.org.
  26. Environment Agency, Dry weather and drought in England: 16 to 22 October 2026 (weekly report, published 23 October 2026) — gov.uk.

Said fairly

We do not claim the water company says it cannot supply these homes. Its position is that it can support growth — and the plan’s position is that water capacity is handled through phasing conditions. Our point is narrower and firmer: in an area of serious water stress, mid-drought, with the data centre’s demand unpublished and no catchment-wide budget, the plan has not demonstrated that this cluster can be supplied and drained — and it has not assessed it as one. That is the gap the examination should test.

Read the evidence

Every figure here is footnoted to a primary source in The Abbots Road Report, alongside the health angle from the BMJ:

Publish the demand. Assess the catchment.

If the water is there, show us. If it isn’t, say so. Either way, the data centre’s water demand should be published and conditioned, and the cluster assessed as a whole.